When a public contract is terminated by mutual agreement, provision shall be made for the payment of compensation to the contractor. In addition to a reasonable amount of compensation for preparatory work and for all costs and expenses arising out of termination, the amount to be paid to the contractor:
(1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and
(2) May, with respect to any other work, be a percent of the contract price equal to the percentage of the work completed. [2003 c.794 §162]