(1) The Department of Environmental Quality may require that plans and specifications for the construction, installation or modification of disposal systems, treatment works and sewerage systems be submitted to the department for its approval or rejection.
(2) If the department requires that plans and specifications be submitted under subsection (1) of this section, construction, installation or modification may not be commenced until the plans and specifications submitted to the department are approved. If the disposal or discharge is for a chemical process mine, as defined in ORS 517.953, departmental review and approval shall be included as part of the consolidated application process under ORS 517.952 to 517.989. Any construction, installation or modification must be in accordance with the plans and specifications approved by the department. [Formerly 468.742; 2005 c.523 §7]
Section: Previous 468B.046 468B.047 468B.048 468B.050 468B.051 468B.052 468B.053 468B.055 468B.060 468B.062 468B.064 468B.065 468B.066 468B.070 468B.075 NextLast modified: August 7, 2008