Oregon Statutes - Chapter 517 - Mining and Mining Claims - Section 517.870 - Adjustment of bond or security of operator upon satisfactory completion of reclamation work.

Upon request of the operator, and when in the judgment of the State Department of Geology and Mineral Industries the reclamation has been completed in accordance with the reclamation plan, the operator shall be notified that the work has been found to be satisfactorily performed and is acceptable and the bond or security of the operator shall be adjusted accordingly. [1971 c.719 §11; 1999 c.492 §7; 2007 c.318 §20]