(1) On the basis of the applicant’s filing or, if there is a hearing, on the record made at the hearing held pursuant to ORS 758.420, the Public Utility Commission shall enter an order either approving or disapproving the contract as filed, together with any appropriate findings of the facts supporting such order.
(2) An order of the commission under this section is subject to judicial review as an order in a contested case in the manner provided by ORS 756.610.
(3) If the commission approves a contract and a petition for judicial review is not filed, the contract shall be deemed to be valid and enforceable for all purposes from the date on which the right to file a petition for judicial review expires. [Formerly 757.630; 1985 c.633 §4; 2005 c.638 §13]
Section: Previous 758.315 758.320 758.400 758.405 758.410 758.415 758.420 758.425 758.430 758.435 758.440 758.445 758.450 758.455 758.460 NextLast modified: August 7, 2008