§ 3922. Payment of retainage to subcontractors.
In the absence of sufficient reason, within 20 days of the receipt of payment by the contractor, the contractor shall pay all subcontractors with which it has contracted their earned share of the payment the contractor received.
Section: Previous 3901 3902 3911 3912 3913 3921 3922 3931 3932 3933 3934 3935 3936 3937 NextLast modified: October 8, 2016