8 Pennsylvania Consolidated Statutes § 2462 - Notice And Failure To Make Required Connection

§ 2462. Notice and failure to make required connection.

An owner shall be given at least 45 days' notice of any ordinance requiring a water connection, and, upon failure of the owner to make the required connection, the borough may make the connection and collect the cost from the owner by a municipal claim or in an action of assumpsit. All connections required shall be uniform.

Section: Previous  2442  2443  2444  2451  2452  2453  2454  2455  2456  2457  2458  2461  2462  2463    Next

Last modified: October 8, 2016