- 6 - insulation board, carbon sidewall blocks, carbon lining paste, and various nuts and bolts. Once it is determined that the cell lining must be replaced, the cell is shunted from the pot line and the carbon anodes are removed. The cell is allowed to cool for 20 hours, and then water is added to further cool the cell and to soften the lining materials. The steel superstructure and the cell shields are removed next, and repairs, if required, are made to the superstructure. The cell lining crew (the crew)4 then removes the cooled, solidified electrolyte and aluminum metal from the cell cavity, and the cell is dug with pot diggers to remove the remaining cell lining. Once the lining has been removed, the shell and shell cradle are taken to the shell repair area for any necessary repairs. A repaired shell and shell cradle are put in the vacant place in the pot line, and the replacement lining is installed in layers. First, the bottom of each shell is lined with two layers of insulating block, and a layer of sheet metal is placed on top of the insulating block to form a vapor barrier. Next, two layers of heavy refractory fire brick are added on top of the metal vapor barrier, and the cathode blocks with embedded steel connector bars are placed in rows on top of the refractory fire 4Vanalco employs between 22 and 26 workers on the crew.Page: Previous 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Next
Last modified: May 25, 2011