Denis H. Dieker, Jr., and Shirley J. Dieker, et al. - Page 3

                                        - 3 -                                         


                    Shareholder                   Amount                              
                    Steven A. Nienke              60.8%                               
                    Vickie L. Nienke              20.0                                
                    John R. Pierce                9.6                                 
                    Denis H. Dieker, Jr.          9.6                                 
                    Total                    100.0                                    
               On or around August 28, 1997, National contracted with                 
          Prairie View Unified School District 362 (the District) to                  
          perform construction work at the Prairie View Middle School and             
          Performing Arts Center (construction contract) for $8,144,300.              
          As part of the construction contract, National was required to              
          obtain a performance bond.  On or around September 5, 1997,                 
          National and Fidelity & Deposit Co. of Maryland (F&D) entered               
          into a separate agreement for an $8,144,300 performance bond (the           
          performance bond).  In the event that National failed to complete           
          the construction work for the project, F&D agreed to act as                 
          surety to the District and was obligated to complete the project.           
          In addition, in a contemporaneous agreement, petitioners,                   
          National, and Midwest Drywall Co., Inc.4 (collectively the                  
          indemnitors), agreed to indemnify F&D for any costs incurred                
          under the performance bond (the indemnity agreement).                       
               On October 22, 1998, the District informed National that it            
          was terminating its employment, asserting that sufficient cause             
          existed under the terms of their contract.  At that time, the               

               4Midwest Drywall Co., Inc., is a company in which                      
          petitioners have an interest.                                               




Page:  Previous  1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  Next