Sec. 2253.046. NOTICE REQUIRED FOR CLAIM FOR PAYMENT OF RETAINAGE. (a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment of retainage, a payment bond beneficiary whose contract with a prime contractor or subcontractor provides for retainage must mail written notice of the claim to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract.
(b) The notice shall consist of a statement of:
(1) the amount of the contract;
(2) any amount paid; and
(3) the outstanding balance.
(c) Notice of a claim for payment of retainage is not required if the amount claimed is part of a prior claim made under this subchapter.
Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1, 1993.
Section: Previous 2253.026 2253.027 2253.041 2253.042 2253.043 2253.044 2253.045 2253.046 2253.047 2253.048 2253.071 2253.072 2253.073 2253.074 2253.075 NextLast modified: September 28, 2016