Texas Government Code § 2253.046 Notice Required For Claim For Payment Of Retainage

Sec. 2253.046. NOTICE REQUIRED FOR CLAIM FOR PAYMENT OF RETAINAGE. (a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment of retainage, a payment bond beneficiary whose contract with a prime contractor or subcontractor provides for retainage must mail written notice of the claim to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract.

(b) The notice shall consist of a statement of:

(1) the amount of the contract;

(2) any amount paid; and

(3) the outstanding balance.

(c) Notice of a claim for payment of retainage is not required if the amount claimed is part of a prior claim made under this subchapter.

Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1, 1993.

Section: Previous  2253.026  2253.027  2253.041  2253.042  2253.043  2253.044  2253.045  2253.046  2253.047  2253.048  2253.071  2253.072  2253.073  2253.074  2253.075  Next

Last modified: September 28, 2016