Sec. 711.063. CONSTRUCTION; DEFAULT. (a) A cemetery in which undeveloped lawn crypt spaces are being sold or reserved for sale shall begin construction on the lawn crypt section not later than 48 months after the date of the first sale or reservation, whichever is earlier, and must complete construction not later than 60 months after the date of the first sale or reservation, whichever is earlier.
(b) If construction of a lawn crypt section described by Subsection (a) does not begin or has not been completed by the dates specified in Subsection (a), on the buyer's written request, the cemetery shall refund the entire amount paid for the undeveloped lawn crypt space not later than the 30th day after the date of the buyer's request.
Added by Acts 2011, 82nd Leg., R.S., Ch. 532 (H.B. 2495), Sec. 4, eff. September 1, 2011.
Added by Acts 2011, 82nd Leg., R.S., Ch. 1336 (S.B. 1167), Sec. 4, eff. September 1, 2011.
Section: Previous 711.052 711.0521 711.053 711.054 711.055 711.056 711.057 711.058 711.059 711.061 711.063 711.064 711.081 711.082 711.083 NextLast modified: September 28, 2016