Sec. 245.005. DORMANT PROJECTS. (a) After the first anniversary of the effective date of this chapter, a regulatory agency may enact an ordinance, rule, or regulation that places an expiration date on a permit if as of the first anniversary of the effective date of this chapter: (i) the permit does not have an expiration date; and (ii) no progress has been made towards completion of the project. Any ordinance, rule, or regulation enacted pursuant to this subsection shall place an expiration date of no earlier than the fifth anniversary of the effective date of this chapter.
(b) A regulatory agency may enact an ordinance, rule, or regulation that places an expiration date of not less than two years on an individual permit if no progress has been made towards completion of the project. Notwithstanding any other provision of this chapter, any ordinance, rule, or regulation enacted pursuant to this section shall place an expiration date on a project of no earlier than the fifth anniversary of the date the first permit application was filed for the project if no progress has been made towards completion of the project. Nothing in this subsection shall be deemed to affect the timing of a permit issued solely under the authority of Chapter 366, Health and Safety Code, by the Texas Commission on Environmental Quality or its authorized agent.
(c) Progress towards completion of the project shall include any one of the following:
(1) an application for a final plat or plan is submitted to a regulatory agency;
(2) a good-faith attempt is made to file with a regulatory agency an application for a permit necessary to begin or continue towards completion of the project;
(3) costs have been incurred for developing the project including, without limitation, costs associated with roadway, utility, and other infrastructure facilities designed to serve, in whole or in part, the project (but exclusive of land acquisition) in the aggregate amount of five percent of the most recent appraised market value of the real property on which the project is located;
(4) fiscal security is posted with a regulatory agency to ensure performance of an obligation required by the regulatory agency; or
(5) utility connection fees or impact fees for the project have been paid to a regulatory agency.
Added by Acts 1999, 76th Leg., ch. 73, Sec. 2, eff. May 11, 1999.
Amended by:
Acts 2005, 79th Leg., Ch. 31 (S.B. 574), Sec. 1, eff. September 1, 2005.
Section: Previous 245.001 245.002 245.003 245.004 245.005 245.006 NextLast modified: September 28, 2016