Texas Local Government Code § 351.140 Payment For Construction Work

Sec. 351.140. PAYMENT FOR CONSTRUCTION WORK. (a) The district shall make monthly progress payments under construction contracts as the work proceeds or at more frequent intervals as determined by the board.

(b) If requested by the board, the contractor shall furnish an analysis of the total contract price showing the amount included for each principal category of the work, in such detail as requested, to provide a basis for determining progress payments.

(c) In making progress payments, the district shall retain 10 percent of the estimated amount until final completion and acceptance of the contract work. However, if the board, at any time after 50 percent of the work has been completed, finds that satisfactory progress is being made, it may authorize any of the remaining progress payments to be made in full. Also, if the work is substantially complete, the board, if it finds the amount retained to be in excess of the amount adequate for the protection of the district, may release to the contractor all or a part of the excess amount.

(d) On completion and acceptance of each separate project, work, or other division of the contract on which the price is stated separately in the contract, payment may be made without retention of a percentage.

(e) When construction work is completed according to the terms of the contract, the board shall draw a warrant on the depository to pay any balance due on the contract.

Added by Acts 1989, 71st Leg., ch. 1, Sec. 74(a), eff. Aug. 28, 1989.

Section: Previous  351.133  351.134  351.135  351.136  351.137  351.138  351.139  351.140  351.141  351.142  351.143  351.144  351.145  351.146  351.147  Next

Last modified: September 28, 2016