Texas Property Code § 53.024 Limitation On Subcontractor's Lien

Sec. 53.024. LIMITATION ON SUBCONTRACTOR'S LIEN. The amount of a lien claimed by a subcontractor may not exceed:

(1) an amount equal to the proportion of the total subcontract price that the sum of the labor performed, materials furnished, materials specially fabricated, reasonable overhead costs incurred, and proportionate profit margin bears to the total subcontract price; minus

(2) the sum of previous payments received by the claimant on the subcontract.

Acts 1983, 68th Leg., p. 3536, ch. 576, Sec. 1, eff. Jan. 1, 1984.

Section: Previous  53.001  53.002  53.003  53.021  53.022  53.023  53.024  53.025  53.026  53.051  53.052  53.053  53.054  53.055  53.056  Next