Texas Special District Local Laws Code § 7807.109 Construction Contracts: Payment

Sec. 7807.109. CONSTRUCTION CONTRACTS: PAYMENT. (a) A contract under Section 7807.107 may be paid for in partial payments as the work progresses, based on estimates approved by the district's engineer.

(b) The payments may not exceed 90 percent of the amount due at the time of such payments as shown by approved estimates, except that on certification by the district's engineer that the project is substantially complete, the board may authorize payment of not to exceed 95 percent of the amount due at the time of such certification before the acceptance of the job and the certificate of completion of the job.

Added by Acts 2011, 82nd Leg., R.S., Ch. 70 (S.B. 1147), Sec. 1.02, eff. April 1, 2013.

Section: Previous  7807.102  7807.103  7807.104  7807.105  7807.106  7807.107  7807.108  7807.109  7807.110  7807.111  7807.112  7807.151  7807.152  7807.153  7807.154  Next

Last modified: September 28, 2016