Sec. 441.134. COMMISSION CONVEYANCE ORDER. (a) Except as provided by Subsections (b) and (c), the commission by order shall authorize the conveyance of a road facility to a governmental entity not later than the 15th day after the date that it receives a board's order to convey.
(b) The commission by order shall delay the conveyance until the district complies with the plans and written commission approvals if:
(1) the commission considers the road facility not to be completed according to the plans and written commission approvals;
(2) the governmental entity to which the road facility is being conveyed files a written protest; or
(3) a municipality in which or extraterritorial jurisdiction of which the road facility is located, if the road facility is being transferred to a county, files a written protest.
(c) An order under Subsection (b) must be issued not later than the 15th day after the later of the date that the commission receives the board's conveyance order or the date a protest is filed.
(d) The commission is not required to hold a hearing before making an order under this section.
Acts 1995, 74th Leg., ch. 165, Sec. 1, eff. Sept. 1, 1995.
Section: Previous 441.114 441.115 441.116 441.117 441.131 441.132 441.133 441.134 441.135 441.136 441.137 441.151 441.152 441.153 441.154 NextLast modified: September 28, 2016