Sec. 251.157. DUTY OF OPERATOR TO PERSON EXCAVATING. (a) Each Class A underground facility operator contacted by the notification system shall mark the approximate location of its underground facilities at or near the site of the proposed excavation if the operator believes that marking the location is necessary. The operator shall mark the location not later than:
(1) the 48th hour after the time the excavator gives to the notification system notice of intent to excavate, excluding Saturdays, Sundays, and legal holidays;
(2) 11:59 a.m. on the Tuesday following a Saturday notification unless the intervening Monday is a holiday;
(3) 11:59 a.m. on the Wednesday following a Saturday notification if the intervening Monday is a holiday; or
(4) a time agreed to by the operator and the excavator.
(b) An operator shall refer to the American Public Works Association color coding standards when marking.
(c) An excavator who has fully complied with this chapter may not be liable for damage to an underground facility that was not marked in accordance with this chapter.
(d) Not later than the 48th hour after the time the excavator gives to the notification center notice of intent to excavate, an operator contacted by the notification center shall notify the excavator of the operator's plans to not mark the proximate location of an underground facility at or near the site of the proposed excavation. The operator must provide the notification by e-mail or facsimile or by another verifiable electronic method approved by the board.
Added by Acts 1999, 76th Leg., ch. 62, Sec. 18.17(a), eff. Sept. 1, 1999. Amended by Acts 2001, 77th Leg., ch. 858, Sec. 2, eff. Nov. 1, 2001.
Section: Previous 251.105 251.106 251.107 251.151 251.152 251.153 251.154 251.155 251.156 251.157 251.158 251.159 251.201 251.2011 251.202 NextLast modified: September 28, 2016