Sec. 35.062. APPLICATION FOR CERTIFICATION. (a) An electric utility or a qualifying facility may submit to the commission for certification a copy of an agreement between the utility and facility for the purchase of capacity.
(b) An agreement submitted for certification under this section may provide that the agreement is contingent on certification by the commission.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.
Section: Previous 35.031 35.032 35.033 35.034 35.035 35.036 35.061 35.062 35.063 35.064 35.065 35.066 35.101 35.102 35.103 NextLast modified: September 28, 2016