Sec. 15.115. CERTIFICATE OF APPROVAL. The executive administrator may consider the following as grounds for refusal to give a certificate of approval for any construction contract:
(1) failure to construct the project according to the approved plans;
(2) failure to construct the works in accordance with sound engineering principles; or
(3) failure to comply with any terms of the contract.
Formerly Sec. 15.112, added by Acts 1981, 67th Leg., 1st C.S., p. 102, ch. 12, Sec. 1, eff. Nov. 10, 1981. Amended by Acts 1985, 69th Leg., ch. 795, Sec. 1.040, eff. Sept. 1, 1985. Renumbered by Acts 1985, 69th Leg., ch. 133, Sec. 2.04. Amended by Acts 1987, 70th Leg., ch. 977, Sec. 12, eff. June 19, 1987.
Section: Previous 15.108 15.109 15.110 15.111 15.112 15.113 15.114 15.115 15.116 15.201 15.202 15.203 15.204 15.205 15.206 NextLast modified: September 28, 2016