Texas Water Code § 60.463 Selecting Contractor For Construction Services Through Competitive Sealed Proposals

Sec. 60.463. SELECTING CONTRACTOR FOR CONSTRUCTION SERVICES THROUGH COMPETITIVE SEALED PROPOSALS. (a) In selecting a contractor for construction, rehabilitation, alteration, or repair services for a facility through competitive sealed proposals, a district shall follow the procedures prescribed by this section.

(b) The district shall select or designate an engineer or architect to prepare construction documents for the project. The selected or designated engineer or architect has full responsibility for complying with Chapter 1001 or 1051, Occupations Code, as applicable. If the engineer or architect is not a full-time employee of the district, the district shall select the engineer or architect as provided by Section 2254.004, Government Code.

(c) The district shall provide or contract for, independently of the contractor, the inspection services, the testing of construction materials, and the verification testing services necessary for acceptance of the facility by the district. The district shall select those services for which it contracts in accordance with Section 2254.004, Government Code, and shall identify them in the request for proposals.

(d) The district shall prepare a request for competitive sealed proposals that includes construction documents, selection criteria, project scope, schedule, and other information that contractors may require to respond to the request. The district shall state in the request for proposals the selection criteria that will be used in selecting the successful offeror.

(e) The district shall receive, publicly open, and read aloud the names of the offerors and, if any lump-sum prices are required to be stated, all such lump-sum prices stated in each proposal. Not later than the 45th day after the date of opening the proposals, the district shall evaluate and rank each proposal submitted in relation to the published selection criteria.

(e-1) Notwithstanding Subsection (e), if the district demonstrates 45 days is not sufficient time for thorough evaluation, the district may specify in the request for competitive sealed proposals a deadline, not later than the 90th day after the date of opening the proposals, to evaluate and rank each proposal submitted in relation to the published selection criteria.

(f) The district shall select the offeror that offers the best value for the district based on the published selection criteria and on its ranking evaluation. The district shall first attempt to negotiate a contract with the selected offeror. The district and its engineer or architect may discuss with the selected offeror options for a scope or time modification and any price change associated with the modification. If the district is unable to negotiate a contract with the selected offeror, the district shall, formally and in writing, end negotiations with that offeror and proceed to the next offeror in the order of the selection ranking until a contract is reached or all proposals are rejected.

(g) In determining best value for the district, the district is not restricted to considering price alone, but may consider any other factor stated in the selection criteria.

Added by Acts 2003, 78th Leg., ch. 307, Sec. 1, eff. June 18, 2003.

Amended by:

Acts 2005, 79th Leg., Ch. 513 (H.B. 769), Sec. 1, eff. September 1, 2005.

Acts 2007, 80th Leg., R.S., Ch. 1330 (S.B. 1531), Sec. 9, eff. June 15, 2007.

Acts 2009, 81st Leg., R.S., Ch. 1191 (H.B. 3785), Sec. 9, eff. June 19, 2009.