Sec. 62.116. INSPECTION OF WORK; PAYMENT. (a) The commission shall inspect the progress of work being done under a contract, and on completion of the contract, the commission shall draw a warrant on the county treasurer payable to the contractor or his assignee for the amount of the contract price. The warrant shall be paid out of the construction and maintenance fund of the district.
(b) If the commission considers it advisable, it may contract for work to be paid for in partial payments as the work progresses. The partial payments may not exceed in the aggregate eighty percent of the total amount to be paid under the contract. The amount of work completed at the time of the partial payment shall be shown by a certificate of the district engineer.
(c) Nothing in this section shall affect the provisions of this chapter providing for the construction of any improvements by the United States.
Acts 1971, 62nd Leg., p. 110, ch. 58, Sec. 1, eff. Aug. 30, 1971. Amended by Acts 1971, 62nd Leg., p. 1770, ch. 518, Sec. 16, eff. May 31, 1971.
Section: Previous 62.109 62.110 62.111 62.112 62.113 62.114 62.115 62.116 62.117 62.118 62.119 62.120 62.121 62.122 62.151 NextLast modified: September 28, 2016