(a)
(b)
(1) The period of the contract, including the number of options to extend the contract and the period for which the contract may be extended under each option, if any.
(2) The maximum quantity or dollar value of the services or property to be procured under the contract.
(3) A statement of work, specifications, or other description that reasonably describes the general scope, nature, complexity, and purposes of the services or property to be procured under the contract.
(c)
(d)
(A) to award a single task or delivery order contract; or
(B) if the solicitation states that the head of the agency has the option to do so, to award separate task or delivery order contracts for the same or similar services or property to two or more sources.
(2) No determination under section 2304(b) of this title is required for award of multiple task or delivery order contracts under paragraph (1)(B).
(3) No task or delivery order contract in an amount estimated to exceed $100,000,000 (including all options) may be awarded to a single source unless the head of the agency determines in writing that—
(A) the task or delivery orders expected under the contract are so integrally related that only a single source can reasonably perform the work;
(B) the contract provides only for firm, fixed price task orders or delivery orders for—
(i) products for which unit prices are established in the contract; or
(ii) services for which prices are established in the contract for the specific tasks to be performed;
(C) only one source is qualified and capable of performing the work at a reasonable price to the government; or
(D) because of exceptional circumstances, it is necessary in the public interest to award the contract to a single source.
(4) The regulations implementing this subsection shall—
(A) establish a preference for awarding, to the maximum extent practicable, multiple task or delivery order contracts for the same or similar services or property under the authority of paragraph (1)(B); and
(B) establish criteria for determining when award of multiple task or delivery order contracts would not be in the best interest of the Federal Government.
(e)
(f)
(g)
(h)
(Added Pub. L. 103–355, title I, §1004(a)(1), Oct. 13, 1994, 108 Stat. 3249; amended Pub. L. 108–136, div. A, title VIII, §843(b), Nov. 24, 2003, 117 Stat. 1553; Pub. L. 108–375, div. A, title VIII, §813(a), Oct. 28, 2004, 118 Stat. 2014; Pub. L. 110–181, div. A, title VIII, §843(a)(1), Jan. 28, 2008, 122 Stat. 236; Pub. L. 111–84, div. A, title VIII, §814(a), Oct. 28, 2009, 123 Stat. 2407; Pub. L. 112–81, div. A, title VIII, §809(b), Dec. 31, 2011, 125 Stat. 1490.)
Sections: Previous 2302 2302a 2302b 2302c 2302d 2303 2304 2304a 2304b 2304c 2304d 2304e 2305 2305a 2306 Next
Last modified: October 26, 2015