(a)
(1) The installation asset manager shall conduct monthly site visits and provide quarterly reports on the progress of the construction or renovation of the housing units. The reports shall be submitted quarterly to the assistant secretary for installations and environment of the respective military department.
(2) The installation asset manager, and, as applicable, the resident construction manager, privatization asset manager, bondholder representative, project owner, developer, general contractor, and construction consultant for the project shall conduct meetings to ensure that the construction or renovation of the units meets performance and schedule requirements and that appropriate operating and ground lease agreements are in place and adhered to.
(3) In the case of a project for new construction, if the project is 90 days or more behind schedule or otherwise appears to be substantially failing to adhere to the obligations or milestones under the contract, the assistant secretary for installations and environment of the respective military department shall submit a notice of deficiency to the Deputy Under Secretary of Defense (Installations and Environment), the Secretary concerned, the managing member, and the trustee for the project.
(4)(A) Not later than 15 days after the submittal of a notice of deficiency under paragraph (3), the Secretary concerned or designated representative shall submit to the project owner, developer, or general contractor responsible for the project a summary of deficiencies related to the project.
(B) If the project owner, developer, or general contractor responsible for the privatization project is unable, within 60 days after receiving a notice of deficiency under subparagraph (A), to make progress on the issues outlined in such notice, the Secretary concerned shall notify the congressional defense committees of the status of the project, and shall provide a recommended course of action to correct the problems.
(b)
(c)
(d)
(e)
(2) Each military department shall consult all records maintained under paragraph (1) when reviewing the past performance of owners, developers, and contractors in the bidding process for a contract or other agreement for a military housing privatization initiative project.
(f)
(A) The financial health and performance of the privatization project, including the debt-coverage ratio of the project and occupancy rates for the housing units.
(B) An assessment of the backlog of maintenance and repair of the housing units.
(2) If the debt service coverage for a military housing privatization project falls below 1.0 or the occupancy rates for the housing units of the project are below 75 percent for more than one year, the Secretary concerned shall require the development of a plan to address the financial risk of the project.
(Added Pub. L. 110–417, div. B, title XXVIII, §2805(a)(1), Oct. 14, 2008, 122 Stat. 4721; amended Pub. L. 112–239, div. B, title XXVIII, §2803(a), Jan. 2, 2013, 126 Stat. 2147; Pub. L. 113–66, div. A, title X, §1084(a)(3), Dec. 26, 2013, 127 Stat. 871.)