(1) Upon application of any electric utility, Federal power marketing agency, geothermal power producer (including a producer which is not an electric utility), qualifying cogenerator, or qualifying small power producer, the Commission may issue an order requiring—
(A) the physical connection of any cogeneration facility, any small power production facility, or the transmission facilities of any electric utility, with the facilities of such applicant,
(B) such action as may be necessary to make effective any physical connection described in subparagraph (A), which physical connection is ineffective for any reason, such as inadequate size, poor maintenance, or physical unreliability,
(C) such sale or exchange of electric energy or other coordination, as may be necessary to carry out the purposes of any order under subparagraph (A) or (B), or
(D) such increase in transmission capacity as may be necessary to carry out the purposes of any order under subparagraph (A) or (B).
(2) Any State regulatory authority may apply to the Commission for an order for any action referred to in subparagraph (A), (B), (C), or (D) of paragraph (1). No such order may be issued by the Commission with respect to a Federal power marketing agency upon application of a State regulatory authority.
Upon receipt of an application under subsection (a) of this section, the Commission shall—
(1) issue notice to each affected State regulatory authority, each affected electric utility, each affected Federal power marketing agency, each affected owner or operator of a cogeneration facility or of a small power production facility, and to the public.1
(2) afford an opportunity for an evidentiary hearing, and
(3) make a determination with respect to the matters referred to in subsection (c) of this section.
No order may be issued by the Commission under subsection (a) of this section unless the Commission determines that such order—
(1) is in the public interest,
(2) would—
(A) encourage overall conservation of energy or capital,
(B) optimize the efficiency of use of facilities and resources, or
(C) improve the reliability of any electric utility system or Federal power marketing agency to which the order applies, and
(3) meets the requirements of section 824k of this title.
The Commission may, on its own motion, after compliance with the requirements of paragraphs (1) and (2) of subsection (b) of this section, issue an order requiring any action described in subsection (a)(1) of this section if the Commission determines that such order meets the requirements of subsection (c) of this section. No such order may be issued upon the Commission's own motion with respect to a Federal power marketing agency.
(1) As used in this section, the term "facilities" means only facilities used for the generation or transmission of electric energy.
(2) With respect to an order issued pursuant to an application of a qualifying cogenerator or qualifying small power producer under subsection (a)(1) of this section, the term "facilities of such applicant" means the qualifying cogeneration facilities or qualifying small power production facilities of the applicant, as specified in the application. With respect to an order issued pursuant to an application under subsection (a)(2) of this section, the term "facilities of such applicant" means the qualifying cogeneration facilities, qualifying small power production facilities, or the transmission facilities of an electric utility, as specified in the application. With respect to an order issued by the Commission on its own motion under subsection (d) of this section, such term means the qualifying cogeneration facilities, qualifying small power production facilities, or the transmission facilities of an electric utility, as specified in the proposed order.
(June 10, 1920, ch. 285, pt. II, §210, as added Pub. L. 95–617, title II, §202, Nov. 9, 1978, 92 Stat. 3135; amended Pub. L. 96–294, title VI, §643(a)(2), June 30, 1980, 94 Stat. 770.)
Sections: Previous 824b 824c 824d 824e 824f 824g 824h 824i 824j 824j-1 824k 824l 824m 824o 824p Next