33 USC 2331 - Use of Continuing Contracts for Construction of Certain Projects

(a) In general

Notwithstanding any other provision of law, the Secretary shall not implement a fully allocated funding policy with respect to a water resource project if initiation of construction has occurred but sufficient funds are not available to complete the project.

(b) Continuing contracts

The Secretary shall enter into a continuing contract for a project described in subsection (a) of this section.

(c) Initiation of construction clarified

For the purposes of this section, initiation of construction for a project occurs on the date of enactment of an Act that appropriates funds for the project from 1 of the following appropriation accounts:

(1) Construction, General.

(2) Operation and Maintenance, General.

(3) Flood Control, Mississippi River and Tributaries.

(Pub. L. 106–53, title II, §206, Aug. 17, 1999, 113 Stat. 286.)