41 USC 3503 - Exceptions

(a) In General.—Submission of certified cost or pricing data shall not be required under section 3502 of this title in the case of a contract, a subcontract, or a modification of a contract or subcontract—

(1) for which the price agreed on is based on—

(A) adequate price competition; or

(B) prices set by law or regulation;

(2) for the acquisition of a commercial item; or

(3) in an exceptional case when the head of the procuring activity, without delegation, determines that the requirements of this chapter may be waived and justifies in writing the reasons for the determination.

(b) Modifications of Contracts and Subcontracts for Commercial Items.—In the case of a modification of a contract or subcontract for a commercial item that is not covered by the exception to the submission of certified cost or pricing data in paragraph (1) or (2) of subsection (a), submission of certified cost or pricing data shall not be required under section 3502 of this title if—

(1) the contract or subcontract being modified is a contract or subcontract for which submission of certified cost or pricing data may not be required by reason of paragraph (1) or (2) of subsection (a); and

(2) the modification would not change the contract or subcontract from a contract or subcontract for the acquisition of a commercial item to a contract or subcontract for the acquisition of an item other than a commercial item.

(Pub. L. 111–350, §3, Jan. 4, 2011, 124 Stat. 3766.)

Historical and Revision Notes
Revised

Section

Source (U.S. Code)Source (Statutes at Large)
3503 41:254b(b). June 30, 1949, ch. 288, title III, §304A(b), as added Pub. L. 103–355, title I, §1251(a)(2), Oct. 13, 1994, 108 Stat. 3279; Pub. L. 104–106, title XLII, §4201(b)(1), Feb. 10, 1996, 110 Stat. 651.