(1) Except to the extent authorized by subsection (b) of this section, the Secretary shall prohibit any powerplant from using natural gas or petroleum under the authority granted him under section 8341(b) or (c) of this title only by means of a final order issued by him which shall be limited to the particular powerplant involved.
(2) The Secretary may issue such a final order only with respect to a powerplant which is not, at the time the proposed order is issued, covered by a final rule issued under subsection (b) of this section.
(1) The Secretary may prohibit, by rule, the use of natural gas or petroleum under section 8341(b) of this title in existing electric powerplants.
(2) Each powerplant to be covered by any final rule issued under this subsection shall be specifically identified in the proposed rule published under section 8411(b) of this title.
(3) In prescribing any final rule under this subsection, the Secretary shall take into account any special circumstances or characteristics of each category of powerplants (such as the intermittent use, size, age, or geographic location of such powerplants). Any such rules shall not apply in the case of any existing electric powerplant with respect to which a comparable prohibition was issued by order.
(Pub. L. 95–620, title III, §303, Nov. 9, 1978, 92 Stat. 3306; Pub. L. 100–42, §1(c)(9), May 21, 1987, 101 Stat. 312.)