(a)
(1) adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
(2) a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
(3) a construction schedule for the project;
(4) a document control procedure and recordkeeping system;
(5) a change order procedure that includes a documented, systematic approach to the handling of construction change orders;
(6) organizational structures, management skills, and staffing levels required throughout the construction phase;
(7) quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
(8) material testing policies and procedures;
(9) internal plan implementation and reporting requirements;
(10) criteria and procedures to be used for testing the operational system or its major components;
(11) periodic updates of the plan, especially related to project budget and project schedule, financing, ridership estimates, and the status of local efforts to enhance ridership where ridership estimates partly depend on the success of those efforts;
(12) the recipient's commitment to submit a project budget and project schedule to the Secretary quarterly; and
(13) safety and security management.
(b)
(2) The Secretary shall inform the recipient of the reasons when a plan is disapproved.
(c)
(d)
(1) a definition of "major capital project" for section 5338(i) that excludes a project to acquire rolling stock or to maintain or rehabilitate a vehicle; and
(2) a requirement that oversight begin during the project development phase of a project, unless the Secretary finds it more appropriate to begin the oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight.
(Pub. L. 103–272, §1(d), July 5, 1994, 108 Stat. 826; Pub. L. 103–429, §6(12), Oct. 31, 1994, 108 Stat. 4379; Pub. L. 104–287, §5(17), Oct. 11, 1996, 110 Stat. 3390; Pub. L. 105–178, title III, §3024, June 9, 1998, 112 Stat. 364; Pub. L. 109–59, title III, §3026, Aug. 10, 2005, 119 Stat. 1622; Pub. L. 112–141, div. B, §20020, July 6, 2012, 126 Stat. 708.)
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
---|---|---|
5327(a) | 49 App.:1619(d), (e). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, §23(b)–(g); added Apr. 2, 1987, Pub. L. 100–17, §324, 101 Stat. 236. |
5327(b) | 49 App.:1619(g). | |
5327(c)(1) | 49 App.:1619(a). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, §23(a); added Apr. 2, 1987, Pub. L. 100–17, §324, 101 Stat. 235; Dec. 18, 1991, Pub. L. 102–240, §3027, 105 Stat. 2115. |
5327(c)(2) | 49 App.:1619(h). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, §23(h); added Nov. 21, 1989, Pub. L. 101–164, §340, 103 Stat. 1099. |
5327(c)(3) | 49 App.:1619(b). | |
5327(d) | 49 App.:1619(c). | |
5327(e) | 49 App.:1619(f). |
Sections: Previous 5319 5321 5322 5323 5324 5325 5326 5327 5329 5330 5331 5332 5333 5334 5335 Next
Last modified: October 26, 2015