Cite as: 503 U. S. 91 (1992)
Opinion of the Court
In the absence of an approved state program, the EPA may issue an NPDES permit under § 402(a) of the Act. (In these cases, for example, because Arkansas had not been authorized to issue NPDES permits when the Fayetteville plant was completed, the permit was issued by the EPA itself.) The EPA's permit program is subject to the "same terms, conditions, and requirements" as a state permit program. 33 U. S. C. § 1342(a)(3). Notwithstanding this general symmetry, the EPA has construed the Act as requiring that EPA-issued NPDES permits also comply with § 401(a). That section, which predates § 402 and the NPDES, applies to a broad category of federal licenses, and sets forth requirements for "[a]ny applicant for a Federal license or permit to conduct any activity including, but not limited to, the construction or operation of facilities, which may result in any discharge into the navigable waters." 33 U. S. C. § 1341(a). Section 401(a)(2) appears to prohibit the issuance of any federal license or permit over the objection of an affected State unless compliance with the affected State's water quality requirements can be ensured.9
in writing to the issuance of such permit, or (B) if the Administrator within ninety days of the date of transmittal of the proposed permit by the State objects in writing to the issuance of such permit as being outside the guidelines and requirements of this chapter. Whenever the Administrator objects to the issuance of a permit under this paragraph such written objection shall contain a statement of the reasons for such objection and the effluent limitations and conditions which such permit would include if it were issued by the Administrator." 33 U. S. C. § 1342(d)(2).
9 Section 401(a)(2) provides, in relevant part: "Whenever such a discharge may affect, as determined by the Administrator, the quality of the waters of any other State, the Administrator . . . shall so notify such other State, the licensing or permitting agency, and the applicant. If, within sixty days after receipt of such notification, such other State determines that such discharge will affect the quality of its waters so as to violate any water quality requirements in such State, and within such sixty-day period notifies the Administrator and the licensing or permitting agency in writing of its objection to the issuance of such license or permit and requests a public hearing on such objection, the licensing or permitting agency shall hold such a hearing. The Administra-
103
Page: Index Previous 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 NextLast modified: October 4, 2007