PUD No. 1 of Jefferson Cty. v. Washington Dept. of Ecology, 511 U.S. 700, 10 (1994)

Page:   Index   Previous  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  Next

Cite as: 511 U. S. 700 (1994)

Opinion of the Court

water through turbines to generate electricity and then return the water to the river below the bypass reach. Under the Federal Power Act (FPA), 41 Stat. 1063, as amended, 16 U. S. C. § 791a et seq., the Federal Energy Regulatory Commission (FERC) has authority to license new hydroelectric facilities. As a result, petitioners must get a FERC license to build or operate the Elkhorn Project. Because a federal license is required, and because the project may result in discharges into the Dosewallips River, petitioners are also required to obtain state certification of the project pursuant to § 401 of the Clean Water Act, 33 U. S. C. § 1341.

The water flow in the bypass reach, which is currently undiminished by appropriation, ranges seasonally between 149 and 738 cubic feet per second (cfs). The Dosewallips supports two species of salmon, coho and chinook, as well as steelhead trout. As originally proposed, the project was to include a diversion dam which would completely block the river and channel approximately 75% of the river's water into a tunnel alongside the streambed. About 25% of the water would remain in the bypass reach, but would be returned to the original riverbed through sluice gates or a fish ladder. Depending on the season, this would leave a residual minimum flow of between 65 and 155 cfs in the river. Respondent undertook a study to determine the minimum stream flows necessary to protect the salmon and steelhead fishery in the bypass reach. On June 11, 1986, respondent issued a § 401 water quality certification imposing a variety of conditions on the project, including a minimum stream flow requirement of between 100 and 200 cfs depending on the season.

A state administrative appeals board determined that the minimum flow requirement was intended to enhance, not merely maintain, the fishery, and that the certification condition therefore exceeded respondent's authority under state law. App. to Pet. for Cert. 55a-57a. On appeal, the

709