Code of Virginia - Title 56 Public Service Companies - Section 56-265.22 Duties of notification center upon notification by person intending to excavate; record of notifica...

§ 56-265.22. Duties of notification center upon notification by person intending to excavate; record of notifica...

A. The notification center shall, upon receiving notice by a person, notify all member operators whose underground lines are located in the area of the proposed project, excavation or demolition. The notification center shall also indicate the names of those operators being notified to the person providing notice.

B. If the notification required by this chapter is made by telephone, a record of such notification shall be maintained by the operators or notification center notified to document compliance with the requirements of this chapter, and such records shall be maintained in compliance with the applicable statute of limitations.

C. The notification center shall notify excavators, within the time frame allowed by the law to mark underground utility lines, of any responses placed on the excavator-operator information exchange system by a locator. Such notification shall occur by facsimile or other mutually acceptable means of automatically transmitting and receiving this information.

If the excavator cannot provide the notification center with a facsimile number or other mutually acceptable means of automatically transmitting and receiving this information, it shall be the excavator's responsibility to contact the excavator-operator information exchange system after the period allowed by law to mark underground facilities and prior to commencing excavation in order to determine if any responses to the notice have been recorded.

(1979, c. 291; 1994, c. 890; 2002, c. 841.)

Sections:  Previous  56-265.17:2  56-265.17:3  56-265.18  56-265.19  56-265.20  56-265.20:1  56-265.21  56-265.22  56-265.22:1  56-265.23  56-265.24  56-265.25  56-265.26  56-265.26:1  56-265.27  Next

Last modified: April 3, 2009