Revised Code of Washington - RCW Title 82 Excise Taxes - Section 82.66.040 Repayment schedule -- Interest, penalties

§ 82.66.040. Repayment schedule -- Interest, penalties

(1) The recipient shall begin paying the deferred taxes in the tenth year after the date certified by the department as the date on which the investment project is operationally complete. The first payment is due on December 31st of the tenth calendar year after such certified date, with subsequent annual payments due on December 31st of the following nine years with amounts of payment scheduled as follows:


Repayment Year % of Deferred Tax Repaid
1 10%
2 10%
3 10%
4 10%
5 10%
6 10%
7 10%
8 10%
9 10%
10 10%

(2) The department may authorize an accelerated repayment schedule upon request of the recipient.

(3) Interest shall not be charged on any taxes deferred under this chapter for the period of deferral, although all other penalties and interest applicable to delinquent excise taxes may be assessed and imposed for delinquent payments under this chapter. The debt for deferred taxes is not extinguished by insolvency or other failure of the recipient.

[1998 c 339 § 1; 1995 c 352 § 4.]

Sections:  Previous  82.66.010  82.66.020  82.66.040  82.66.050  82.66.060  82.66.900  82.66.901  Next

Last modified: April 7, 2009