§ 60.13.030. Preparer lien for grain, hay, or straw
Starting on the date a producer delivers grain, hay, or straw to a preparer, the producer has a first priority statutory lien, referred to as a "preparer lien." This preparer lien shall continue twenty days after payment for the product is due and remains unpaid, without filing any notice of lien, for the contract price, if any, or the fair market value of the products delivered. The preparer lien attaches to the agricultural products delivered by the producer to the preparer, and to the preparer's accounts receivable.
[1985 c 412 § 3.]
Sections: Previous 60.13.010 60.13.020 60.13.030 60.13.035 60.13.040 60.13.050 60.13.060 60.13.070 NextLast modified: April 7, 2009