§ 60.28.040. Tax liens -- Priority of liens
The amount of all taxes, increases and penalties due or to become due under Title 82 RCW, from a contractor or the contractor's successors or assignees with respect to a public improvement contract wherein the contract price is twenty thousand dollars or more shall be a lien prior to all other liens upon the amount of the retained percentage withheld by the disbursing officer under such contract, except that the employees of a contractor or the contractor's successors or assignees who have not been paid the prevailing wage under such a public improvement contract shall have a first priority lien against the bond or retainage prior to all other liens. The amount of all other taxes, increases and penalties due and owing from the contractor shall be a lien upon the balance of such retained percentage remaining in the possession of the disbursing officer after all other statutory lien claims have been paid.
[1985 c 80 § 1; 1971 ex.s. c 299 § 1; 1955 c 236 § 4. Prior: 1949 c 228 § 27, part; Rem. Supp. 1949 § 8370-204a, part; RCW 82.32.250, part.]
Notes:
Severability -- Effective dates -- 1971 ex.s. c 299: See notes following RCW 82.04.050.
Sections: Previous 60.28.010 60.28.011 60.28.015 60.28.020 60.28.021 60.28.030 60.28.040 60.28.050 60.28.051 60.28.060 60.28.080 60.28.900 Next
Last modified: April 7, 2009