§ 78.44.111. Segmental reclamation -- Primary objective

The permit holder shall reclaim each segment of the mine within two years of completion of surface mining on that segment except as provided in a segmental reclamation agreement approved in writing by the department. The primary objective of a segmental reclamation agreement should be to enhance final reclamation.

[1993 c 518 § 5.]