Revised Code of Washington - RCW Title 39 Public Contracts And Indebtedness - Section 39.10.270 Project review committee -- Certification of public bodies

§ 39.10.270. Project review committee -- Certification of public bodies

(1) A public body may apply for certification to use the design-build or general contractor/construction manager contracting procedure, or both. Once certified, a public body may use the contracting procedure for which it is certified on individual projects with a total project cost over ten million dollars without seeking committee approval. The certification period is three years. A public body seeking certification must submit to the committee an application in a format and manner as prescribed by the committee. The application must include a description of the public body's qualifications, its capital plan during the certification period, and its intended use of alternative contracting procedures.

(2) To certify a public body, the committee shall determine that the public body:

(a) Has the necessary experience and qualifications to determine which projects are appropriate for using alternative contracting procedures;

(b) Has the necessary experience and qualifications to carry out the alternative contracting procedure including, but not limited to: (i) Project delivery knowledge and experience; (ii) personnel with appropriate construction experience; (iii) a management plan and rationale for its alternative public works projects; (iv) demonstrated success in managing public works projects; (v) demonstrated success in managing at least one general contractor/construction manager or design-build project within the previous five years; (vi) the ability to properly manage its capital facilities plan including, but not limited to, appropriate project planning and budgeting experience; and (vii) the ability to meet requirements of this chapter; and

(c) Has resolved any audit findings on previous public works projects in a manner satisfactory to the committee.

(3) The committee shall, if practicable, make its determination at the public meeting during which an application for certification is reviewed. Public comments must be considered before a determination is made. Within ten business days of the public meeting, the committee shall provide a written determination to the public body, and make its determination available to the public on the committee's web site.

(4) The committee may revoke any public body's certification upon a finding, after a public hearing, that its use of design-build or general contractor/construction manager contracting procedures no longer serves the public interest.

(5) The committee may renew the certification of a public body for one additional three-year period. The public body must submit an application for recertification at least three months before the initial certification expires. The application shall include updated information on the public body's capital plan for the next three years, its intended use of the procedures, and any other information requested by the committee. The committee must review the application for recertification at a meeting held before expiration of the applicant's initial certification period. A public body must reapply for certification under the process described in subsection (1) of this section once the period of recertification expires.

(6) Certified public bodies must submit project data information as required in RCW 39.10.320 and 39.10.350.

[2007 c 494 § 107.]

Notes:
     Sunset Act application: See note following chapter digest.

Sections:  Previous  39.10.200  39.10.210  39.10.220  39.10.230  39.10.240  39.10.250  39.10.260  39.10.270  39.10.280  39.10.290  39.10.300  39.10.310  39.10.320  39.10.330  39.10.340  Next

Last modified: April 7, 2009