Revised Code of Washington - RCW Title 70 Public Health And Safety - Section 70.79.250 Inspection -- Frequency -- Grace period

§ 70.79.250. Inspection -- Frequency -- Grace period

In the case of power boilers a grace period of not more than two months longer than the period established by the board under RCW 70.79.240(1) may elapse between internal inspections of a boiler while not under pressure or between external inspections of a boiler while under pressure; in the case of low pressure heating boilers not more than twenty-six months shall elapse between inspections, and in the case of unfired pressure vessels not more than two months longer than the period between inspections prescribed by the board shall elapse between internal inspections.

[1993 c 391 § 2; 1951 c 32 § 23.]

Sections:  Previous  70.79.180  70.79.190  70.79.200  70.79.210  70.79.220  70.79.230  70.79.240  70.79.250  70.79.260  70.79.270  70.79.280  70.79.290  70.79.300  70.79.310  70.79.320  Next

Last modified: April 7, 2009