§ 47.28.120. Actions for labor and materials -- Limitation of action
Any contracting person, firm, or corporation performing any labor or furnishing any materials upon their contract or otherwise for public work or improvement under the direction of the department or any person claiming any right of action upon any such contract with the state of Washington or who claims a cause of action against the state of Washington arising out of any such contract must bring such suit in the proper court in Thurston county before the expiration of one hundred and eighty days from and after the final acceptance and the approval of the final estimate of such work by the department; otherwise the action is forever barred.
[1984 c 7 § 173; 1961 c 13 § 47.28.120. Prior: 1937 c 53 § 40; RRS § 6400-40.]
Notes:
Severability -- 1984 c 7: See note following RCW 47.01.141.
Sections: Previous 47.28.050 47.28.060 47.28.070 47.28.075 47.28.080 47.28.090 47.28.100 47.28.110 47.28.120 47.28.140 47.28.150 47.28.170 47.28.220 47.28.241 47.28.251 Next