§ 80.28.170. Testing at consumer's request
If any consumer to whom a meter has been furnished shall request the commission in writing to inspect such meter, the commission shall have the same inspected and tested, and if the same, on being so tested, shall be found to be more than four percent if an electric meter, or more than two percent if a gas meter, or more than two percent if a water meter, defective or incorrect to the prejudice of the consumer, the expense of such inspection and test shall be borne by the gas company, electrical company or water company, and if the same, on being so tested shall be found to be correct within the limits of error prescribed by the provisions of this section, the expense of such inspection and test shall be borne by the consumer.
[1961 c 14 § 80.28.170. Prior: 1911 c 117 § 74, part; RRS § 10410, part.]
Sections: Previous 80.28.100 80.28.110 80.28.120 80.28.130 80.28.140 80.28.150 80.28.160 80.28.170 80.28.180 80.28.185 80.28.190 80.28.200 80.28.220 80.28.230 80.28.240 NextLast modified: April 7, 2009