Alaska Statutes Title 34, Chapter 34.35, Article 06 - Timber and Lumber
- Sec. 34.35.230 Construction.
The purpose of AS 34.35.230 - 34.35.315 is remedial to secure laborers, contractors, and subcontractors the amount due them for labor performed in producing,...
- Sec. 34.35.235 Persons Entitled to Timber Lien.
(a) The following persons shall have liens upon timber for the work done upon, or in obtaining or securing, or for services rendered in...
- Sec. 34.35.240 Lien Claim.
(a) A person who claims a lien under AS 34.35.235 within 60 days after the completion of the service or after the close of...
- Sec. 34.35.245 Landowner's Lien for Timber.
A person who permits another to go upon the person's land and cut timber has a lien upon the timber for the price agreed...
- Sec. 34.35.250 Landowner's Lien Claim.
(a) A person who claims a lien under AS 34.35.245 must record, within 90 days from the cutting of the timber, a claim with...
- Sec. 34.35.255 Priority.
(a) Liens under AS 34.35.230 - 34.35.315 are preferred liens and are prior to other liens. A sale or transfer of timber does not...
- Sec. 34.35.260 Duration of Lien.
(a) A lien under AS 34.35.230 - 34.35.315 does not bind property for more than six months after notice of the lien is recorded,...
- Sec. 34.35.265 Enforcement of Lien Against Manufactured Product.
(a) The lien provided for saw logs and shingle bolts is not released or lost by the manufacture of the saw logs or shingle...
- Sec. 34.35.270 Commissioner of Public Safety As Receiver.
(a) The commissioner of public safety or a peace officer designated by the commissioner shall be the receiver, when one is appointed, and the...
- Sec. 34.35.275 Bona Fide Purchasers.
The court shall conclusively presume that a party purchasing the property liened upon within the 60 days given to claimants to record their liens...
- Sec. 34.35.280 Enforceability.
(a) The following persons may demand that a lien under AS 34.35.230 - 34.35.315 be enforced:(1) a person who brings an action to enforce...
- Sec. 34.35.285 Contractor's Lien.
A person who, as a contractor, supplies lumber under a contract is entitled to the lien under AS 34.35.230 - 34.35.315 to the amount...
- Sec. 34.35.290 Order of Sale Before Judgment.
(a) The court or judge may in vacation, upon motion supported by affidavit showing that the property is liable to loss or destruction, order...
- Sec. 34.35.295 Liability for Injuring Property or Destroying Identity.
(a) A person who eloigns, injures, or destroys or who makes difficult, uncertain, or impossible the identification of timber upon which there is a...
- Sec. 34.35.300 Lien for Manufacturing.
(a) A person who performs work or assists in manufacturing timber into lumber has a lien upon the lumber while it remains at the...
- Sec. 34.35.305 Manufacturing Lien Claim.
(a) A person who desires to claim the benefit of AS 34.35.300 shall, within 60 days after the close of the service mentioned in...
- Sec. 34.35.310 Release Upon Filing Bond.
(a) After a lien attaches to property mentioned in AS 34.35.230 - 34.35.315, the owner of the property or a person on behalf of...
- Sec. 34.35.315 Definitions.
In AS 34.35.230 - 34.35.315,(1) "lumber" includes timber, or lumber or shingles manufactured from it;(2) "timber" includes saw logs, piles, spars, cordwood, fuelwood, shingle...
Last modified: November 15, 2016