48-2053. Option of sanitary district to reject bids; sanitary district as contractor; limitation of assessment
The board may, within ten days after the time fixed for opening bids, by resolution adopted by a vote of two-thirds of its members, order that the proposed contract not be entered into and that the sanitary district itself perform the work according to the plans and specifications as adopted for the work. If it is so ordered, the district shall be considered the contractor. The district shall not be permitted to assess an amount in excess of the amount proposed by the lowest responsible bidder or, if no bids have been received, in excess of the amount of the estimate.
Section: Previous 48-2046 48-2047 48-2048 48-2049 48-2050 48-2051 48-2052 48-2053 48-2054 48-2055 48-2056 48-2057 48-2058 48-2059 48-2060 NextLast modified: October 13, 2016