Ex parte COHEN et al. - Page 6




          Appeal No. 2000-0076                                                        
          Application 08/970,231                                                      


               Biffis, the examiner’s primary reference, discloses a                  
          building production line 10 located on-site in the midst of a               
          subdivision 80 of building lots 82 (see Figure 8).  As                      
          described in the reference,                                                 
                    production line 10 is a factory-like facility in                  
                    which two parallel production lines, 11 and 12,                   
                    are placed side by side.  The production lines                    
                    each include its own railway track 14, 15                         
                    extending through the assembly facility past a                    
                    basic construction area 16 and then past a                        
                    plurality of bays 18 providing storage space for                  
                    light construction and finishing materials such                   
                    as window frames and doors, plumbing and                          
                    electrical supplies.  Basic construction area 16                  
                    and bays 18 are collectively referred to as                       
                    “work stations”.  Running on the tracks 14 and                    
                    15 are a plurality of transporting devices 20                     
                    each comprising a flatbed 21 (see FIG. 2) having                  
                    a series of railway track engaging wheels 22                      
                    there beneath and anti-friction surfaces, such                    
                    as roller conveyors 24, on the upper surfaces of                  
                    the flatbed.                                                      
                         As the devices 20 proceed from left to                       
                    right as seen in FIG. 1, the building unit 30 is                  
                    erected on the base member of the system . . .                    
                    .  Fabrication of the building unit 30 continues                  
                    throughout the production line until finally it                   
                    is rolled out to a loading bay 25 on the right                    
                    hand side of FIG. 1.  Here a means to transport                   
                    the prefabricat[ed] building unit to the                          
                    building site is provided in the form of a                        
                    flatbed truck 26 which is dimensioned so that                     
                    the building unit 30 can be slid off the roller                   
                    conveyors 24 on the flatbed 21, onto the flatbed                  
                    27 of the truck 26 which itself has an anti-                      
                    friction surface on top of its flatbed, which                     
                    anti-friction surface may be a roller conveyor                    
                    28 similar to the roller conveyor 24.                             
                                          6                                           




Page:  Previous  1  2  3  4  5  6  7  8  9  10  11  12  13  14  Next 