[§269-145] Grid access; procedures for interconnection; dispute resolution. (a) Each user, owner, or operator of the Hawaii electric system, or any other person, business, or entity seeking to make an interconnection on the Hawaii electric system shall do so in accordance with procedures to be established by the commission by rule or order.
(b) The commission shall have the authority to make final determinations regarding any dispute between any user, owner, or operator of the Hawaii electric system, or any other person, business, or entity connecting to the Hawaii electric system, concerning either an existing interconnection on the Hawaii electric system or an interconnection to the Hawaii electric system created under the processes established by the commission under this section. [L 2012, c 166, pt of §2]
Section: Previous 269-133 269-134 269-135 269-141 269-142 269-143 269-144 269-145 269-145.5 269-146 269-147 269-148 269-149 269-161 269-162 NextLast modified: October 27, 2016