(220 ILCS 5/9-216) (from Ch. 111 2/3, par. 9-216)
Sec. 9-216. The Commission shall establish, by rulemaking, the policies and procedures which shall be utilized in evaluating and deciding any requests for the recovery and allocation of reasonable and prudent costs incurred in the construction of generation or production facilities which have been cancelled. In establishing such policies and procedures the Commission shall consider all relevant factors, including, but not limited to, the prudence and reasonableness of such costs, the reasons for cancellation, the consistency of construction and cancellation with certification and reevaluation criteria and proceedings, the need to provide proper incentives for future construction and cancellation decisions, and the balance of equities between ratepayers and shareholders.
(Source: P.A. 90-655, eff. 7-30-98.)
Sections: Previous 9-210.5 9-211 9-212 9-213 9-214 9-215 9-215.1 9-216 9-217 9-220 9-220.1 9-220.2 9-220.3 9-221 9-222 Next