The withholding of retainage by a contractor or subcontractor on public improvement contracts shall be in accordance with ORS 701.420 and 701.430 except when the charter of the contracting agency contains provisions requiring retainage by the contracting agency of more than five percent of the contract price of the work completed. [2003 c.794 §147]
Section: Previous 279C.527 279C.528 279C.530 279C.535 279C.540 279C.545 279C.550 279C.555 279C.560 279C.565 279C.570 279C.580 279C.585 279C.590 279C.600 NextLast modified: August 7, 2008