(1) A person claiming to have supplied labor or materials for the performance of the work provided for in a public contract, including any person having a direct contractual relationship with the contractor furnishing the payment bond or a direct contractual relationship with any subcontractor, or an assignee of such person, or a person claiming moneys due the State Accident Insurance Fund Corporation, the Unemployment Compensation Trust Fund or the Department of Revenue in connection with the performance of the contract, has a right of action on the contractor’s payment bond as provided for in ORS 279C.380 and 279C.400 only if:
(a) The person or the assignee of the person has not been paid in full; and
(b) The person gives written notice of claim, as prescribed in ORS 279C.605, to the contractor and the contracting agency.
(2) When, upon investigation, the Commissioner of the Bureau of Labor and Industries has received information indicating that one or more workers providing labor on a public works have not been paid in full at the prevailing rate of wage or overtime wages, the commissioner has a right of action first on the contractor’s public works bond required under ORS 279C.836 and then, for any amount of a claim not satisfied by the public works bond, on the contractor’s payment bond, as provided in ORS 279C.380 and 279C.400. When an investigation indicates that a subcontractor’s workers have not been paid in full at the prevailing rate of wage or overtime wages, the commissioner has a right of action first on the subcontractor’s public works bond and then, for any amount of a claim not satisfied by the subcontractor’s public works bond, on the contractor’s payment bond. The commissioner’s right of action exists without necessity of an assignment and extends to workers on the project who are not identified when the written notice of claim is given, but for whom the commissioner has received information indicating that the workers have provided labor on the public works and have not been paid in full. The commissioner shall give written notice of the claim, as prescribed in ORS 279C.605, to the contracting agency, the Construction Contractors Board, the contractor and, if applicable, the subcontractor. The commissioner may not make a claim for the same unpaid wages against more than one bond under this section. [2003 c.794 §154; 2005 c.360 §3]
Section: Previous 279C.555 279C.560 279C.565 279C.570 279C.580 279C.585 279C.590 279C.600 279C.605 279C.610 279C.615 279C.620 279C.625 279C.650 279C.655 NextLast modified: August 7, 2008