No later than March 1 of each odd-numbered year, the State Board of Higher Education shall submit a report to the Legislative Assembly concerning the status of all previously approved Department of Higher Education capital construction projects that have not been completed or have been completed within the preceding 24-month period. The report shall include the project title, funding sources, the amount of the original appropriation or expenditure limitation, the amount of unexpected funds, the construction status and the anticipated completion date. [1991 c.647 §3; reenacted by 1993 c.538 §2; reenacted by 1995 c.254 §4]
Note: 351.165 was made a part of ORS chapter 351 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.