Oregon Statutes - Chapter 517 - Mining and Mining Claims - Section 517.820 - Extensions of time for submission of proposed reclamation plans; time limit for reclamation completion; consultation with state agencies.

(1) Upon good cause shown, the State Department of Geology and Mineral Industries may grant reasonable extensions of time for the completion by the landowner or operator and the submission to the department of a proposed reclamation plan required by ORS 517.790. Each reclamation plan submitted to the department must provide that all reclamation activities shall be completed within three years after the termination of mineral extraction from the surface mining operation conducted within each separate area for which an operating permit is requested. Each such reclamation plan shall be approved by the department if it adequately provides for the reclamation of surface-mined lands.

(2) The department, prior to approving a proposed reclamation plan, shall consult with all other interested state agencies and appropriate local planning authorities. [1971 c.719 §5; 1977 c.59 §2; 2007 c.318 §17]

Section:  Previous  517.780  517.785  517.790  517.795  517.800  517.810  517.815  517.820  517.830  517.831  517.832  517.833  517.834  517.835  517.836  Next

Last modified: August 7, 2008