Oregon Statutes - Chapter 549 - Drainage and Flood Control Generally - Section 549.340 - Construction; functions of county surveyor or county engineer; performance by landowner.

If the county court authorizes the improvement, it shall be done under the direction and supervision of the county surveyor, or the county engineer, who shall set all necessary grade stakes and bench marks. The owner of any of the lands through which or on which any portion of the improvement is to be constructed may, at the expense of the owner, perform such construction work under the supervision of the county surveyor, or the county engineer. If the owner does not elect to do such work, it shall be done by the county under the direction and supervision of the county surveyor, or the county engineer. [Amended by 1965 c.287 §2]

Section:  Previous  549.160  549.170  549.180  549.190  549.310  549.320  549.330  549.340  549.350  549.360  549.370  549.380  549.390  549.400  549.510  Next