Oregon Statutes - Chapter 701 - Construction Contractors and Contracts - Section 701.430 - Performance bond; terms; effect of not obtaining bond.

(1) Except as provided in subsection (2) of this section, a contractor or subcontractor may execute and deliver to the owner, contractor or subcontractor before the commencement of construction for which the contractor or subcontractor will be responsible for performing a good and sufficient bond in a sum equal to the contract price for the faithful performance of the contract. The term of the bond required under this subsection shall extend to include the period during which claims of lien or notices of other encumbrances based on the construction performed under the contract may be filed under applicable law. The bond must be approved by the owner, contractor or subcontractor entitled to withhold retainage. A faithful performance bond delivered under this section shall include, but not be limited to, provisions to the effect that:

(a) The obligations of the contract shall be faithfully performed;

(b) Payment shall promptly be made to all persons supplying labor or materials to the contractor or subcontractor for prosecution of the work provided in the contract;

(c) All contributions due the Industrial Accident Fund and the State Unemployment Compensation Fund from the contractor or subcontractor in connection with the performance of the contract shall promptly be made; and

(d) All sums required to be deducted and retained from the wages of employees of the contractor or subcontractor pursuant to the Personal Income Tax Act of 1969, shall be paid over to the Department of Revenue.

(2) When a contractor or subcontractor does not obtain the bond required under subsection (1) of this section, the owner, contractor or subcontractor may withhold that percentage of the contract price of the work completed as retainage that is agreed to by the parties to the contract. The owner, contractor or subcontractor shall pay interest at the rate of one percent per month on the final payment due a contractor or subcontractor who was unable to obtain the bond required under subsection (1) of this section. The interest shall commence 10 days after the date on which claims of lien or notices of other encumbrances based on the construction performed under the contract must be properly filed under applicable law. For purposes of this subsection, “final payment due a contractor or subcontractor” means the amount withheld as retainage minus the total dollar amount of liens and other encumbrances resulting from the failure of the contractor or subcontractor to faithfully perform the obligations of the contract and properly filed within the time allowed under applicable law. [1975 c.772 §3]

Note: See note under 701.410.

Section:  Previous  701.340  701.345  701.348  701.350  701.355  701.410  701.420  701.430  701.435  701.440  701.500  701.505  701.510  701.515  701.525  Next

Last modified: August 7, 2008