If the owner of any structure or improvement served from the overhead electric or communication service facilities within an underground assessment district does not grant the utility a permit or easement referred to in ORS 758.250 or if such an owner fails to convert to underground service facilities within 90 days after the mailing to the owner of the notice provided by ORS 758.245, the public authority shall order the utility to complete the conversion and to disconnect and remove all overhead facilities, including service facilities, providing service to such structure or improvement. [1969 c.385 §10]
Section: Previous 758.220 758.225 758.230 758.235 758.240 758.245 758.250 758.255 758.260 758.265 758.270 758.280 758.282 758.284 758.286 NextLast modified: August 7, 2008